      华阳河蓄滞洪区老堤质量检测与评价研究

      Study on quality inspection and evaluation for old embankments of Huayang River Flood Storage and Detention Area

      • 摘要: 为掌握华阳河蓄滞洪区建设工程(安庆市)老堤的质量现状, 提出了以面波法进行普查,以便携式动力触探进行详查的点-线结合式质量检测方法, 并以复华段老堤为研究对象开展现场试验, 获得了面波波速和锥尖阻力随深度变化的关系曲线, 提出了相应的压实度评价标准;结合渗流数值分析, 对老堤填筑质量进行了评价, 提出了相应的处理措施。结果表明:随压实度增大,面波波速整体呈增加趋势, 平均锥尖阻力与老堤压实度呈现明显的正相关关系;普查采用93%压实度对应的172 m/s面波波速为标准, 详查分别采用88%、90%和93%压实度对应的锥尖阻力作为标准, 得到老堤堤身压实度随深度方向呈“上下大、中间小”的分布特征;老堤压实度较差时, 堤身存在渗透稳定问题, 可采用防渗墙等措施进行处理。研究成果可为类似工程提供参考。

         

        Abstract: In order to master the filling quality of the old embankment in the Huayang River Flood Storage and Detention Area Construction Project (Anqing City), a point line combined quality inspection method using surface wave method for general survey and portable dynamic penetration for detailed survey was proposed. Taking the Fuhua section embankment as the research object, on-site experiments were carried out to obtain the relationship curve between the surface wave velocity and cone tip resistance of the old embankment body with depth changes. The corresponding compaction evaluation criteria were proposed, and the filling quality of the old embankment was assessed through numerical seepage analysis, and corresponding treatment measures were proposed. The results showed that the surface wave velocity presented an overall increasing trend with the increase of compaction degree, and the average cone tip resistance was significantly positively correlated with the compaction degree of the old embankment. The survey used a surface wave velocity of 172 m/s corresponding to 93% compaction as the standard. For detailed investigations, the cone tip resistance values corresponding to 88%, 90%, and 93% compaction levels were adopted as standards, revealing a distribution characteristic of the old embankment body where compaction was higher at the top and bottom, but lower in the middle along the depth direction. When the compaction degree of the old embankment is low, there is a problem of seepage stability in the embankment body, which can be treated by measures such as cut-off walls.The research results can provide a reference for similar embankment projects.

         

      /

      返回文章
      返回